I would hope that everyone is aware that work has finally begun on the Ralph Butcher Causeway.
The work is expected to last 22 weeks until December 8.
There has been a lane closure in place on on bridge at King’s Dyke since July 2024 due to cracking in the road.
In May 2025, contractor, Jones Bros reported further cracks that had appeared in the road surface near the centre of the carriageway.
The costs for the works are being fully met by Jones Bros. The council will not accept ownership of the bridge until the remediation work is addressed.
A spokesperson for Cambridgeshire County Council said: “The work will be carried out and completed with the existing single lane closure.