A message from the King’s Dyke project team:

We have been laying the final layer of tarmac – the surface course – around the western roundabout (pictured far left and right), and traffic will be moved permanently onto the roundabout from 3 May.

Traffic lights will be needed for a week to allow the western tie-in works by Funthams Lane to be completed, while the new bus stops will also come into use on 3 May.

The embankment works on the site have progressed well, with the section closest to the railway bridge now completed.

This has allowed work to start on the construction of the reinforced concrete slabs (centre picture), which will form the foundations for the edge protection that extends out from the bridge