KD X Update

A message from the King’s Dyke project team:

The site team have completed the pile cap and anchor beam works with all 24 bars installed. The stone layer (pictured left) has been placed over the top ready for the reinforced earth embankment works to start.

Kerbing has been completed on the western roundabout (pictured right), with the associated tie-in works ready to commence in the New Year. With all the major structures now completed, we will be starting to connect the new road to the existing one from 10 January and this will involve temporary traffic management on the road – find out more details here

We would like to thank all residents and commuters for their patience in 2021