We would like to thank everyone for their patience during the traffic lights on the A605 whilst Jones Bros constructed a new site access. The temporary traffic lights have been removed after the work was completed ahead of schedule.
The site team are now halfway through their programme to partially fill Star Pit quarry. Once completed, Jones Bros will build the embankment and road on top of the filled section.

The two main structures, the bridge and the underpass, continue to move along the construction programme well, and it was fantastic to see the progress on site during our visit.