A message from the King’s Dyke project team: 

We’re pleased to say that work is progressing well, with the partial filling of Star Pit reaching the point where the whole area is now above water.
Work will continue here until the level reaches that of the bridge.
 

There has also been progress on the embankment next to the eastern abutment for the railway bridge, with it now at the right height for a crane to be brought in to lift the beams for the bridge into place. 

The bridge beams themselves will be lifted into place throughout Sunday 9 May.

Due to the size of the beams, there will be minimal temporary traffic management for short periods starting from 7pm on Friday 8 May to 5pm on Sunday 9 May.
This will allow us to get the beams onto site for the lift to take place.  

We would like to thank you for your patience while these works take place as swiftly and safely as possible.