KD X Update 10th June 2022


(click on picture to enlarge)

The remainder of the surfacing works that link the western roundabout and the eastern roundabout have now started (pictured left).
The vehicle restraint system is also being installed either side of the road along this section.

The surfacing works have also been completed around the eastern roundabout (pictured right), ready for the tie-in works to start at the eastern end in just over two weeks’ time.

Prior to that, works were concentrated towards the middle section of the scheme, around the underpass and railway bridge, which isn’t particularly visible to the public eye.