KD X Update

A message from the King’s Dyke project team:

The reinforced concrete anchor beam, which is part of the piling reinforcement near Star Pit, has now been completed.

The capping beam, which will then sit on the top of the piles and is also made of reinforced concrete, is progressing well. The steel reinforcement (pictured right) is now in place with half of the concrete poured.

Near the western tie-in, work on drainage is now well underway. The majority of the kerbs have also been installed, with the shape of the footpath (pictured left) that will run alongside it now evident.

Lastly, for those that would like to give feedback on the project, our online communications survey closes at midnight tonight (26 November).