The resurfacing schemes listed in the previous email will be delivered by our contractor Tarmac, on behalf of Cambridgeshire County Council.
The scheduled start dates and durations for the work are all detailed on our website.
The work will be carried out on site Monday – Friday only unless weather causes delays.
Please bear in mind that the programme for the two B1040 schemes and the B1095 is sequential in nature, so delays on one scheme may affect the delivery dates of those following on.
Please note that due to the deep excavation being carried out to repair the road, four of the schemes in this year’s package will be delivered under a 24/7 closure.
This means that for the duration of the work the road won’t be available as a through route for traffic or emergency vehicles.
The first scheme to commence will be the B1040 Ramsey Road on 12th August, the A1101 Mildenhall will follow on a week later on the 19th August, once the work on the B1382 is complete.
I am aware this work will cause disruption to local stakeholders, we will however be working closely with our contractor to reduce this as much as possible. We have set up a dedicated email address and phone number for the duration of the work, these will go ‘live’ shortly, in addition we have also created our own web page. Emails and phone calls will all be responded to within 24hrs of receipt. Letters will be sent out to local businesses and residents two weeks in advance. Prior to the work commencing, a CCC officer and member of Tarmac will also be visiting any businesses located within the extents of each scheme to discuss both the delivery process and any concerns they may have regarding access arrangements.
The following is a link to the web page that has been created for this year’s EHA package – www.cambridgeshire.gov.uk/resurfacing-works/
In the first instance please direct all enquiries to this page. Overview locations for each of the five schemes are included, along with a downloadable copy of each diversion route –