I Have Asked Questions – A605

Having received a number of complaints (not from my ward area) from residents concerning the issue – traffic light/management on the A605 – I have asked our two County Councillors questions on behalf of these residents.

1/ Why we as Councillors are not being communicated with when the road only opened on Thursday late afternoon.

2/ What is the problem/issue.

3/ Why isn’t the work being done over the weekend to minimise the disruption come Monday morning.

4/ Why is there no penalty involved with the developer/contactor if delays like this occur.

 

 

 

Just received an e-mail from Cllr Dee Laws….
Due to the heavy rain on Thursday  there was a flash flood outside the Lindum Homes site which caused a small sinkhole to be created. They had to carry out emergency repairs today under 2-way traffic management. I am not sure if the repairs are yet complete but the timing is unfortunate the day after the road had reopened.

This entry was posted in News. Bookmark the permalink.