The surfacing works have now started at the eastern roundabout (pictured right), which is opposite Forterra.
Elsewhere, the embankment between the railway bridge and the underpass structure is now nearly level, which has allowed works to start on the reinforced concrete slabs (pictured left) that sit on top of the embankment behind the railway bridge.